Abstract
Progressive Powder Coating in Mentor, Ohio, is a metal finishing plant that uses a convection oven in its manufacturing process. In an effort to save energy and improve production, the company installed an infrared oven in between the powder coating booth and the convection oven on its production line. This installation allowed the plant to increase its conveyor line speed and increase productionby 50 percent. In addition, the plant reduced its natural gas consumption, yielding annual energy savings of approximately $54,000. With a total project cost of $136,000, the simple payback is 2.5 years.
| Original language | American English |
|---|---|
| Publisher | National Laboratory of the Rockies (NLR) |
| Number of pages | 4 |
| State | Published - 2003 |
NLR Publication Number
- NREL/BR-840-33095
Other Report Number
- DOE/GO-102003-1656
Keywords
- case study
- convection oven
- energy savings
- industrial energy efficiency
- infrared oven
- manufacturing
- metal finishing
- natural gas
- plant-wide assessments
- powder coating
Fingerprint